Traffic Delays Likely in Chiswick

Forthcoming significant roadworks in the W4 area

 
Participate

Bookmark and Share

Traffic and Travel in Chiswick

Sign up for our weekly Chiswick newsletter

Comment on this story on the

The following roadworks are likely to cause some delays in the Chiswick area

chiswick roadworks

Nine Month Delay to Gunnersbury Avenue Roadworks
Power Road bridge project lane closures to continue until autumn 2018

A4 Great West Road, Brentford

25 June — 29 June

Delays likely Lane closure

Works description: 22:00hrs to 05:00hrs Lane 3,2 closure eastbound for pier monitoring and removal of delaminating concrete

Responsibility for works: Highways England

Current status: Planned work about to start

Works reference: FN59340914

A4 Great West Road, Brentford

25 June — 29 June

Delays likely Lane closure

Works description: 22:00hrs to 05:00hrs Lane 3,2 closure Westbound for pier monitoring and removal of delaminating concrete

Responsibility for works: Highways England

Current status: Planned work about to start

Works reference: FN59340915

A4 Great West Road, Brentford

25 June — 29 June

Delays likely Lane closure

Works description: Install dual lay HV duct in F/W.

Responsibility for works: GAS TRANSPORTATION CO LTD

Current status: Planned work about to start

Works reference: ZP011P91252N00186191/R13

A4 Great West Road, Brentford

25 June — 20 July

Delays likely Lane closure

Works description: 22:00hrs to 05:00hrs Lane 3,2 closure Eastbound and Westbound for pier monitoring and removal of delaminating concrete

Responsibility for works: Highways England

Current status: Planned work about to start

Works reference: FN59340924

Whitehall Park Road, Chiswick

26 June — 29 June

Delays likely Road closure

Works location: Unknown

Works description: PFI CARRIAGEWAY MICRO SURFACING

Responsibility for works: Hounslow

Current status: Advanced planning

Works reference: FQ00830051598

A205 Chiswick High Road (North Circular Road), Chiswick

16 June — 02 July

Delays likely Lane closure

Works description: ****SECTION 50**** Completion of works on GCL main and lay gas pipe (following trial holes) NTC02A: Road space to be occupied CW: 24/7 on these dates only: 16th/17th June, 23rd/24th June, 30th June and 1st July (Sat/Sun only) NCT02B: Extended working hours 07.00-19.00 Sat & Sun NCT05A: Works restricted to area agreed in TfL reference: W18-0436 - Lane 1 Closure Southbound Site contact: Ian North 07920 231 306

Responsibility for works: Transport for London

Current status: Planned work about to start

Works reference: YG104L-MAIN-00006121/UL2

Hardwicke Road, Chiswick

18 June — 31 October

Delays likely Road closure

Works description: Microsurfacing

Responsibility for works: Ealing

Current status: Planned work about to start

Works reference: DV00665000529

A316 Burlington Lane, Chiswick

5 Mar - 29 June

Delays likely Road closure

Works description: Cadent are carrying out essential gas maintenance in the road to replace old iron gas mains with more durable plastic pipes. This is to ensure we continue to provide safe and reliable gas supplies to local businesses and residents

Responsibility for works: Cadent

Current status: In progress

Works reference: YG430284435

Gunnersbury Avenue (North Circular Road)

7 Jun 2017 - 16 Nov 2018

Delays likely Lane Closure

Works description:1 northbound lane closed, one running lane maintained northbound and two southbound. Traffic lanes will be realigned on the carriageway to suit phases of work during demolition of the main bridge. Lanes will first be slewed to the east and then to the west.

Responsibility for works: Transport For London

Current status: Work in progress


Source: www.roadworks.org

June 29, 2018

Bookmark and Share