Planned roadworks in the W4 area
The following roadworks are likely to cause some delays in the Chiswick area:
Major Work Begins On Chiswick Bridge
Delay and disruption is likely on the A316 (Great Chertsey Rd) near Chiswick Bridge due to road and others works: The areas affected are;
Great Chertsey Road (A316)
24 March — 25 April
Delays likely Lane closure
Works location: Footway Adjacent To Junction Of Hartington Road. Fault In Great Chertsey Road (A316)
Works description: Cable Fault Rectification
Responsibility for works: National Grid Company
Current status: Planned work about to start
Burlington Lane, Chiswick |
22 April — 23 April |
Delays likely Road closure |
Works location: Hogarth Carbridge |
Works description: Urgent Structure Inspections Full Closure Eb Night Works |
Responsibility for works: Transport For London |
Current status: Planned work about to start |
|
Great West Road |
23 April — 23 April |
Delays likely Lane closure |
Works location: Chiswick To Hogarth |
Works description: Wp Block Closure Wb# Testing Lights& Bollards, Bulk Clean & Change, Sweeping, Gully & Beany Block Cleaning, Barrier Works, Grass Cutting, Sign Cleaning, Debris Patrols Offside Lane Closures With Nearside Lane Running - All Vehicle Movements Maintained E/B 0000 To 0500 Slip No Nw12-0365 |
Responsibility for works: Transport For London |
Current status: Work in progress |
|
Great West Road |
23 April — 24 April |
Delays likely Lane closure |
Works location: Hogarth To Chiswick |
Works description: Cpp1 Block Closure Wb# Testing Lights& Bollards, Bulk Clean & Change, Sweeping, Gully & Beany Block Cleaning, Barrier Works, Grass Cutting, Sign Cleaning, Debris Patrols Offside Lane Closures With Nearside Lane Running - All Vehicle Movements Maintained Wb 0000 To 0500 Slip No Nw12-0365 |
Responsibility for works: Transport For London |
Current status: Work in progress |
|
Source: www.roadworks.org
April 22, 2014
|