Planned roadworks in the W4 area
The following roadworks are likely to cause some delays in the Chiswick area:
Major Work On Chiswick Bridge to Spring 2015
Chiswick Bridge will be closed from Saturday morning at 01.00 until Monday morning at 04.00 on the following dates:
• Saturday 28 February until Monday 2 March 2015
• Saturday 7 March until Monday 9 March 2015
Signed diversion routes will be in place at Chiswick Bridge. Drivers are strongly advised to plan alternative routes to avoid this delay.
More Overnight Closures For Hammersmith Flyover to Spring 2015
B490 Acton Lane, Chiswick |
22 February — 25 February |
Delays likely Road closure |
Works location: B490 |
Works description: S81 Planned Cover Replacement--Works Intended To Include First Time Permanent Reinstatement Within Same Phase |
Responsibility for works: Thames Water |
Current status: Advanced planning
|
A406 Gunnersbury Avenue (North Circular Road) |
24 February — 25 February |
Delays likely Lane closure |
Works location: A406 |
Works description: Cpp Block Closure Wb# Testing Lights& Bollards, Bulk Clean & Change, Sweeping, Gully & Beany Block Cleaning, Barrier Works, Grass Cutting, Sign Cleaning, Debris Patrols Offside Lane Closure With Nearside Lane Running - All Vehicle Movements Maintained 22:00 - 05:00 |
Responsibility for works: Transport For London |
Current status: Advanced planning
|
|
A4 Chiswick Roundabout, Chiswick |
25 February — 27 February |
Delays likely Lane closure |
Works location: A4 |
Works description: Carriageway Patch - Outer Ring Switch Inner Ring Night Works 23:00 To 0500 Nb/Sb/Eb/Wb |
Responsibility for works: Transport For London |
Current status: Planned work about to start
|
|
B491 Turnham Green Terrace, Chiswick |
25 February — 25 February |
Delays likely Traffic control (multi-way signals) |
Works location: B491 |
Works description: S81 Emergency Cover Replacemen--Works Intended To Include First Time Permanent Reinstatement Within Same Phase |
Responsibility for works: Thames Water |
Current status: Planned work about to start
|
|
A316 Burlington Lane, Chiswick |
26 February — 27 February |
Delays likely Traffic control (multi-way signals) |
Works location: A316 |
Works description: Remedial Works Following Defect Inspection To Rectify Core Defect In Carriageway |
Responsibility for works: National Grid Gas Plc |
Current status: Planned work about to start |
|
Source: www.roadworks.org
February 25, 2015
|